November 16, 2026
SB 9, a state law in force since January 2022, requires cities to consider a second home on a single-family lot, or the split of the lot in two, ministerially, without discretionary review or a hearing, when the project meets the law's conditions (Senate Bill 9). In Los Angeles each project needs a building permit. The City's permit record has no SB 9 field, so this report finds SB 9 projects from each permit's description.
We counted every City of Los Angeles building permit that cites SB 9, from the first in June 2022 to October 31, 2026: 1,877 homes on 1,742 permits, plus 584 ADUs on the same permits. Outside Brentwood – Pacific Palisades, SB 9 went from nothing to about a third of new-house permits, and nine SB 9 homes in ten are in the San Fernando Valley.
This report publishes the figures and the dataset. It does not argue for a cause. Where a number invites one, the competing readings are listed and left open. For what to check on a lot before building, see our Lot Due Diligence Report.
The Dataset
- Source: City of Los Angeles open data, dataset
pi9x-tg5x, Building and Safety permits issued from 2020 to present. Public, with permits issued through November 7, 2026. - Unit: a home added by a building permit whose description cites SB 9, its code sections (65852.21 and 66411.7) or a "two-unit development", counted from the City's dwelling-unit field and checked against the description.
- Every count is a floor. The permit record has no SB 9 field, so a project whose permit never names the law can't be found.
- Revisions are removed (232 permits), and so are 107 permits that turn an existing ADU or second unit into the SB 9 unit (Finding 6).
- Matched windows. Every year is cut to January 1 – October 31, so 2026 is compared like-for-like.
- These are permits. Finished homes are measured only through certificates of occupancy (Finding 7). Two-unit developments are permitted by the Department of Building and Safety. Urban lot splits are parcel maps filed with City Planning, so the splits themselves are not counted here.
Finding 1: SB 9 Went From Nothing to a Third of New Houses Outside the Palisades
Outside Brentwood – Pacific Palisades, 5 new-house permits cited SB 9 between January 1 and October 31, 2022. In 2025 it was 258, 36.0% of new-house permits, and in 2026 it is 161, or 31.9%. Citywide, with the Palisades fire rebuild in the count, the 2026 share is 11.8%.
Share of new single-family house permits whose description cites SB 9, issued January 1 – October 31 of each year. The law took effect in January 2022.
Counting every kind of SB 9 home (new houses, duplex units, additions and conversions), the City permitted 686 in 2025, the most in a full year so far. By October 31, 2026 it had permitted 517, 10.2% fewer than at the same point of 2025. Other new houses outside the Palisades fell by more, 25.1% (458 to 343).
SB 9 homes permitted January 1 – October 31 of each year. Full-year totals are shown for completed years.
Finding 2: Nine SB 9 Homes in Ten Are in the San Fernando Valley
Since January 2023, 90.3% of SB 9 homes are in the North Valley and South Valley planning areas. SB 9 accounts for 86.9% of new-house permits in Granada Hills – Knollwood and 2.5% in West Los Angeles.
Share of new-house permits that cite SB 9 since January 2023: the six highest and six lowest of the 29 community plan areas with at least 30 new houses (SB 9 homes of every kind in brackets). Every area is in the CSV below.
| Most SB 9 homes since January 2023 | SB 9 homes | New houses | SB 9 share |
|---|---|---|---|
| Canoga Park – West Hills – Winnetka – Woodland Hills | 244 | 139 | 61.2% |
| Reseda – West Van Nuys | 211 | 115 | 82.6% |
| Sun Valley – La Tuna Canyon | 183 | 116 | 75.0% |
| Van Nuys – North Sherman Oaks | 171 | 197 | 37.6% |
| North Hollywood – Valley Village | 128 | 127 | 33.9% |
| Mission Hills – Panorama City – North Hills | 119 | 82 | 58.5% |
SB 9 homes include additions and conversions, so an area can have more SB 9 homes than SB 9 new houses. The share column counts new-house permits only.
Finding 3: The Gap Holds on Flat Single-Family Lots
This comparison sets hillside sites aside. On flat lots in single-family zones (R1, RS, RA or RE, outside the Hillside Ordinance area), with the Palisades left out, SB 9 is 79.9% of new houses in the North Valley and 3.2% in West Los Angeles. On the same kind of lot, that is about 25 times the share.
| Planning area (flat single-family lots) | New houses | Under SB 9 | Share |
|---|---|---|---|
| North Valley | 452 | 361 | 79.9% |
| South Valley | 738 | 326 | 44.2% |
| East Los Angeles | 25 | 6 | 24.0% |
| South Los Angeles | 50 | 12 | 24.0% |
| Harbor | 36 | 7 | 19.4% |
| Central | 45 | 3 | 6.7% |
| West Los Angeles | 253 | 8 | 3.2% |
New-house permits issued January 2023 – October 31, 2026, Brentwood – Pacific Palisades excluded.
Inside the Valley, 50.4% of new houses on flat lots cite SB 9, against 5.0% in the hillside area. Outside the Valley the two shares are close, at 3.7% on flat lots and 3.8% on hillsides.
Finding 4: Nine SB 9 Parcels in Ten Have No House-Demolition Permit
Of the 1,877 SB 9 homes, 829 (44.2%) are new detached houses, 558 (29.7%) are additions to the existing house that create a second unit, 270 (14.4%) are in 135 new duplexes, and 220 (11.7%) are conversions of a garage, rec room, storage building or accessory quarters.
SB 9 homes by kind, June 2022 – October 31, 2026.
92.6% of SB 9 parcels (1,569 of 1,694) have no house-demolition permit. New duplexes are the exception: 78 of 131 duplex parcels (59.5%) replaced a demolished house. A lot split can change the parcel number, so the no-demolition share is an upper bound. Only 18 SB 9 building permits mention a lot split. The split itself is a parcel map filed with City Planning, so it doesn't appear in this data.
Finding 5: Four in Ten SB 9 Permits Also Add an ADU
In 2022, 12.5% of SB 9 permits added an ADU on the same permit. The share rose every year to 39.3% in 2025 and stands at 39.2% in 2026. SB 9 permits since 2022 also include 584 ADUs. On 681 parcels these permits add up to two homes, counting SB 9 units and ADUs together, and on 35 to three or more.
Share of SB 9 permits that add an ADU on the same permit, January 1 – October 31 of each year. Our ADU Permit Report covers ADUs of every kind.
Finding 6: 107 SB 9 Permits Re-Designate an Existing Unit
107 permits turn an existing ADU, junior ADU or older second unit into the SB 9 unit. They don't create a new home, so this report does not count them. Four permits go the other way and turn an SB 9 unit into an ADU.
| Year | Re-designations |
|---|---|
| 2022 | 1 |
| 2023 | 9 |
| 2024 | 26 |
| 2025 | 33 |
| 2026* | 25 |
January 1 – October 31 of each year. * 2026 to date.
Finding 7: Similar Permit Times, Earlier Certificates of Occupancy
Across the city outside the Palisades, SB 9 houses reach a permit in a median of 193 days from application, against 445 for other new houses. On flat single-family lots in the Valley the medians are 188 days for SB 9 houses and 182 for other new houses.
| New houses issued since January 2023 | SB 9 median | Other median | Permits |
|---|---|---|---|
| Outside the Palisades, wildfire rebuilds excluded | 193 days | 445 days | 760 / 2,426 |
| Flat single-family lots in the Valley | 188 days | 182 days | 687 / 503 |
Days from application to permit issue. The clock includes time the application spends with the applicant, and only permits that were issued are counted.
On those lots, a larger share of SB 9 houses had a certificate of occupancy within 18 months of the permit. Of the houses permitted in 2023, 65.0% of SB 9 houses had one within 18 months, against 51.5% of other new houses. At 24 months it is 73.0% against 62.6%. Fewer SB 9 permits describe a two-story house: 50.5% of SB 9 houses on these lots are described as two or more stories, against 78.3% of other new houses.
| Permits issued in | SB 9 within 18 months | Other within 18 months |
|---|---|---|
| 2023 | 65.0% (65 of 100) | 51.5% (84 of 163) |
| 2024 | 57.1% (101 of 177) | 45.6% (67 of 147) |
Flat single-family lots in the Valley, wildfire rebuilds excluded. Each cohort is every house permitted that year, and each has had the full 18 months, so recent permits do not flatter the result. Shares are a floor: some finished houses carry no certificate date. Our Home Build Timeline Report measures construction time for all new houses.
Finding 8: 12 SB 9 Homes in Brentwood – Pacific Palisades Since 2023
Brentwood – Pacific Palisades has 12 SB 9 homes since January 2023, against 1,533 new-house permits. Eight of the ten permits are in ZIP code 90049 (Brentwood) and one is in 90402. One is in 90272, the Pacific Palisades ZIP code: a duplex whose permit carries wildfire-rebuild wording, applied for on June 30, 2025.
On July 30, 2025 the Governor's Executive Order N-32-25 suspended SB 9 in the very high fire hazard severity zones of the Palisades and Eaton fire areas and let local agencies set their own rules there. The same day, Mayor Bass's Emergency Executive Order No. 9 ordered that the City "will not accept or process applications under Government Code Sections 65852.21 and 66411.7 for any project within a Very High Fire Hazard Severity Zone within the boundaries of the Palisades Fire area." The Mayor's order exempts complete plan-check applications accepted before the Governor's order. The data can't separate the orders' effect, because SB 9 was already near zero there: 3 homes in 2024.
Possible Readings
- The Valley concentration fits several explanations: the larger minimum lot sizes of RS and RA zones, the value of one large house against two smaller homes in different parts of the city, rents, a local network of designers and builders who may have learned the process, and the law's site exclusions, such as contributing buildings in historic districts and very high fire hazard zones that don't meet fire-mitigation standards. The gap holds on flat lots (Finding 3), so slope alone does not account for it. Lot size, prices and the exclusions aren't in the permit record, so the data can't test them.
- The rise from 2023 to 2025 fits the time a new law takes to learn, rising rents or lenders getting used to SB 9 projects. It also fits SB 450, in force from January 1, 2025, which requires local standards to apply the same way as in the underlying zone and sets a 60-day deadline after which an application is deemed approved. The share had already doubled in 2024, before SB 450, and the data can't separate these.
- The rising ADU share fits builders getting the most homes out of one lot, or the ADU rules getting easier. The record doesn't say why.
- Re-designations. An SB 9 unit is a primary dwelling, and after an urban lot split each parcel can hold its own home. An ADU stays accessory to the main house. The record doesn't say whether that difference is the reason owners re-designate.
- Earlier certificates of occupancy fit fewer two-story buildings, smaller houses, repeat designs or financing pressure. The data doesn't record why.
- What to watch. City Planning's SB 9 FAQ, revised August 24, 2026, says the City implements SB 9 through an interdepartmental memo, last revised that day, and that its Missing Middle LA initiative, launched in October 2025, will create a new code section for SB 9. It also says AB 1061 (2025) allows two-unit developments on historic-district sites with non-contributing structures (City Planning SB 9 FAQ).
Opportunity Spotlight
- In the North Valley, SB 9 is now the usual route to a new house on a flat lot (79.9%). There is plenty of local precedent: 361 of 452 new houses on those lots since 2023.
- On West Los Angeles' flat single-family lots it is close to unused (3.2%), so the option is little tested there.
- Budget the normal permit time. On flat single-family lots in the Valley, SB 9 houses took about as long to permit as other new houses, a median of about six months (188 days) from application.
- 92.6% of SB 9 parcels have no house-demolition permit, and four SB 9 permits in ten now add an ADU as well.
Method
- Finding SB 9 permits. The permit has no SB 9 field, so each permit is found from its description, which names the law about ten ways ("SB9", "SB-9", "Senate Bill 9", the code sections 65852.21 and 66411.7, "two-unit development", and misspellings). Run-on text is handled: "per SB91 OF 2" is SB 9 followed by "1 of 2". A hand check of 30 random matches found all 30 to be SB 9 work. A search of the other new-house permits outside the Palisades since 2023 for second-unit and SB 9 code wording found 2 SB 9 projects written as "SENATE BILL 9TWO-UNIT", and the rule was widened to include them.
- Revisions. A supplemental permit revises an earlier one: an original's middle block ends in 0000 and a revision counts up from it. Original-numbered permits described as "supplemental to permit #…" are removed as well.
- Homes. Each permit's homes come from the City's
du_changedfield, corrected where the description contradicts it. A new duplex counts two and any other permit at most one, because house-to-duplex conversions record two but add one. 126 permits with no unit recorded (carports, grading, pools, remodels) count zero. A hand read of the 74 building permits among them found 32 that describe a new SB 9 unit, a few of them one of several permits for the same project, so the home count is low by up to 1.7%. ADUs come fromadu_changedon the permits that create an SB 9 home. Junior ADUs (26) are not included. - Re-designations are permits whose ADU count goes down by one (85), or whose description converts an existing ADU or second unit into the SB 9 unit (22). A hand read of those 22 found 20 clear cases and 2 that convert only part of an ADU.
- Zones and slope. A single-family zone is one beginning R1, RS, RA or RE after any (T), (Q) or [Q] prefixes (99.7% of SB 9 permits are in one). Hillside means the record's Hillside Ordinance Area flag. Community plan area names that the record truncates are merged.
- Completion is the share of a whole year's permits with a certificate of occupancy within a fixed number of months, published only once every permit in that year has had the full period.
- Cross-checks. Every published figure was recomputed by a second, independent program and matched exactly, and the portal's own server-side counts of the yearly SB 9 share agree within one permit. In the City's Annual Progress Report data for the state, 620 of this report's 634 SB 9 permits issued in 2025 (97.8%) are tagged SB 9, and 93.4% in 2024. Of the 70 state rows for 2025 that this report does not count, 36 are re-designated units, which this report excludes by design, 30 are revision or supplemental permits, and 4 are permits this report does not find as SB 9 permits (APR data).
- Not used: the
square_footagefield, which doesn't consistently match the size stated in the description, and declared valuation, which is a permit-fee figure.
Download the Data
The processed dataset is published for reuse. Attribution to Blackbriar is welcome but not required. The underlying records are the City of Los Angeles'.
- sb9-homes-by-year.csv: SB 9 homes and permits by year in the matched window, by kind, with ADUs added, re-designations and full-year totals
- sb9-share-of-new-houses.csv: new-house permits and the SB 9 share by year, citywide and outside the Palisades
- sb9-by-community-plan-area.csv: SB 9 homes, new houses and the SB 9 share by community plan area since 2023
- sb9-permit-timing.csv: application-to-issue days for SB 9 and other new houses
- sb9-permits.json: the complete dataset, including counts at every cleaning step, the flat-lot and hillside tests, demolitions, completion, the Palisades permits, the state cross-check, source metadata and caveats
How Blackbriar Uses This
We design and build homes, additions and ADUs in Los Angeles. This record shows where SB 9 homes have been permitted, what kind they are and how long the permits took. Our services and process pages set out how we work, our ADU Permit Report covers the other common way to add a home, and you can talk to us directly.
FAQ
How many homes has SB 9 produced in Los Angeles?
City of Los Angeles building permits that cite SB 9 cover 1,877 homes on 1,742 permits from the first, issued in June 2022, to October 31, 2026, plus 584 ADUs on the same permits. 2025 had the most in a full year so far, 686. The count covers only permits whose description names the law, so it is a floor.
Where in Los Angeles is SB 9 used most?
In the San Fernando Valley, which has 90.3% of the SB 9 homes permitted since January 2023. By community plan area, SB 9 accounts for 86.9% of new-house permits in Granada Hills – Knollwood and 2.5% in West Los Angeles.
Does SB 9 get a building permit faster in Los Angeles?
On comparable lots the times are about the same: on flat single-family lots in the Valley, the median from application to permit issue since 2023 is 188 days for SB 9 houses and 182 days for other new houses. Across the city outside the Palisades the medians are 193 and 445 days, a gap that disappears when SB 9 houses are compared with new houses on the same kind of lot.
How often do SB 9 projects in Los Angeles add an ADU?
39.3% of SB 9 permits issued between January 1 and October 31, 2025 added an ADU on the same permit, and 39.2% in 2026, up from 12.5% in 2022. SB 9 permits since 2022 also include 584 ADUs.
How much SB 9 building is there in Pacific Palisades?
12 SB 9 homes in Brentwood – Pacific Palisades since January 2023, against 1,533 new-house permits, and one SB 9 permit in ZIP code 90272. On July 30, 2025 the Mayor ordered the City not to accept SB 9 applications in the very high fire hazard zone of the Palisades fire area.
How many SB 9 parcels in Los Angeles have a house-demolition permit?
7.4% of parcels with an SB 9 permit also have a house-demolition permit on the same parcel number, and 92.6% have none. On parcels with a new SB 9 duplex it is 59.5%. A lot split can change the parcel number, so some demolitions may be missed.
Where does this data come from?
From the City of Los Angeles open data portal, dataset pi9x-tg5x (Building and Safety permits issued from 2020 to present), with permits issued through November 7, 2026. Blackbriar found SB 9 permits from their descriptions, removed revisions and re-designated units, checked the City's unit counts against the text and published the results as CSV and JSON files. 97.8% of this report's 2025 permits are also tagged SB 9 in the City's annual report to the state.
Recommended
- 2026 Los Angeles ADU Permit Report: every ADU and junior ADU the City has permitted since 2020
- 2026 Los Angeles Residential Building Permit Report: new houses and ADUs by area
- 2026 Los Angeles Lot Due Diligence Report: what to check on a lot before building